Project: Assisted Conception Unit, Ninewells Hospital, Dundee.
Client: NHS Tayside
Principal Contractor: Morrison Construction
Contract Value: £2.3M

The existing Assisted Conception Unit that is currently located in Ward 35 of Ninewells Hospital, Dundee no longer meets the requirements of new legislation governing fertility clinics. The proposed site for the new facility consists of the existing Ward 35 facility within Ninewells and a new infill development spread over three floors. After consideration it was agreed that the current facility will remain in operation during the course of the works. The project will have to be phased into stages to allow the continued operation of the current facility. The project is being developed and delivered under Frameworks Scotland and the principal contractors input at design stage is invaluable when assessing the practicalities of building within an occupied hospital environment.

Other issues being considered relate to traffic management within the grounds of an occupied hospital and existing service connections.

Project: Nuclear Medicine Departments, Ninewells Hospital & PRI
Client: NHS Tayside
Principal Contractor: Morrison Construction
Contract Values: £3.5M & £700,000.

Ninewells - The project involves the construction of a new build nuclear medicine facility adjacent and connected to the main hospital building. The main issues being considered include the location of the site adjacent to the main hospital access road, maintaining fire escape routes and live services within the site.

Perth Royal Infirmary - The project incorporates a 2 level refurbishment within the existing hospital and a new build plant room for the nuclear medicine facility and proposed endoscopy unit. There is an existing loading bay and access corridor that require to remain accessible throughout the works and there will be an interface between staff and patients using the hospital and areas of the site.

Both projects are being developed and delivered under Frameworks Scotland.

Project: Pharmacogenomics Lab Refurbishment, Ninewells Hospital & Medical School
Client: University of Dundee
Principal Contractor: Mansell Plc
Contract Value: £1.5M

The works comprise the alteration / refurbishment of existing laboratory facilities including extensive mechanical and electrical upgrade to provide new laboratories, freezer room, offices, write up areas and ancillary facilities. The works also include the advanced works of the relocation of the nitrogen store.

Access for operatives, material and debris were through fully occupied areas of the hospital. Contractor access for material delivery and debris removal was limited to certain times and a rigorous cleaning regime was undertaken. High specification temporary partitions were required to ensure that dust ingress to other lab areas was eliminated.

The works were successfully completed in January 2010.

Project: Window Replacement, Dundee Dental Hospital
Client: NHS Tayside Estates & Buildings
Principal Contractor: Muirfield Contracts
Contract Value: £100,000

The works comprise the replacement of windows to the west elevation (10 storeys in height) and associated internal linings and reinstatement of ventilation where required.

The height of the building is obviously an issue along with the area immediately surrounding the west elevation which comprised of a University car parking area. Parts of the dental hospital are to remain operational throughout the works which requires temporary partitions to be erected in line with infection control standards. The fire escape stair windows are to be replaced whilst a continual safe escape route is maintained.

The works are due to commence in March 2010.

Project: Armitstead Child Development Centre, Kings Cross Hospital, Dundee
Client: NHS Tayside
Principal Contractor: Mansell Plc
Contract Value: £3.0M

Armitstead Child Development Centre is a multi-disciplinary centre for children with development delay and disabilities. It consists of a multi-disciplinary assessment resource for pre-school and school age children, an outpatient paediatric therapy resource for pre-school and school age children, an integrated therapy nursery for pre-school age children and outpatient clinics for pre-school and school age children.

NHS Tayside propose a purpose built building to house all of the above, situated within the grounds of Kings Cross Hospital, Clepington Road, Dundee. The main issues of concern related to the existing environment and were mainly security and ongoing vandalism, traffic management and adjacent building sites within the hospital grounds.

These issues were successfully dealt with through close liaison between the principal contractor and the client and also liaison with adjacent contractors ensuring that access for all sites remained unobstructed at all times and deliveries etc were pre-arranged.

The building was successfully completed in August 2008.
Project: Refurbishment - Ward 9, Kings Cross Hospital, Dundee
Client: NHS Tayside
Principal Contractor: various
Contract Value: £1.7 million

Ward 9 is an existing single storey building situated within the grounds of Kings Cross Hospital in Dundee. It is the old Infectious Diseases ward and has been lying empty for 5 to 6 years. The building is in generally good condition but continuing vandalism has resulted in external windows having to be fully boarded up.

NHS Tayside propose to house a number of Community Therapy departments within this one building. The project has been split into three separate contracts, Re-roofing works, Enablement works and the main building works contract. This requires the development of three pre tender health & safety plans each covering the specific health & safety plans and issues relating to each work package.

All three work packages raised the same issues in relation to the existing environment which are mainly security and ongoing vandalism, the fully operational adjacent x-ray department and traffic management within the hospital grounds.

All 3 phases have been successfully completed with all departments now fully operational.
Welcome Sign, Ninewells Hospital, Dundee Project: Refurbishment - Ward 12, Ninewells Hospital, Dundee
Client: NHS Tayside
Principal Contractor: Mansell Plc
Contract Value: £1M

The works comprise of alterations to existing patient toilet/shower facilities and the upgrading of existing services/finishes throughout the ward including installation of a new nurse call system, upgrading/replacement of electrical installation, heating, medical gases and water services and replacement wall, floor and ceiling finishes.

Access to the ward which is situated on Level 6 of the hospital is via an existing window opening. Ward 12 has fully occupied wards and clinics above and below so privacy and noise issues are a concern. Traffic management, infection control and residual asbestos within the building were all issues covered by the design team and incorporated in the pre-construction information. Works are due to start imminently with Mansell Plc as the Principal Contractor.
Project: Community Midwife Unit, Ninewells Hospital, Dundee
Client: NHS Tayside
Principal Contractor: TBC
Contract Value: £ 2.4 million

The works comprise the alteration of the existing hospital to create new Community Maternity Unit and Outpatient Services within existing Level 6 and Level 7 areas. Works include the construction of a new plant room, main entrance and associated external works to be carried out in 3 separate phases.

Traffic management is a major issue as the new plantroom excavations intrude on the existing access road and the redirection of an existing water main crosses over the access road in 2 places. The design team worked together to produce the right information to communicate all the risk information to the contractor for inclusion in the pre-construction information. Works are due to start on site in August 2007.
Diabetic Centre, Ninewells Hospital, Dundee Project: Diabetic Centre, Ninewells Hospital, Dundee
Client: NHS Tayside
Principal Contractor: Clachan Construction
Contract Value: £ 650,000

The works comprise of internal alteration and refurbishment of existing Level 7 including reconfiguration of layouts, redecoration, floor covering, electrical installation, mechanical and ventilation along with associated works in connection with services outwith Level 7.

Traffic management was looked at in great detail as there was a contractor working on the adjacent site with access scaffolding extending over Clachan Constructions site. A meeting with all parties involved resolved the compound/access/scaffolding issues and the project was successfully completed in July 2007 without incident.